liquidated and unliquidated damages and penalty
Section 74 of the Indian Contract Act, 1872, read with section 73
In one minute
Sometimes a contract fixes in advance what a party must pay if he breaks it. Sometimes it says nothing, and the court works out the loss afterwards. Section 74 deals with the first case. It says that the injured party gets reasonable compensation, and never more than the sum named.
Indian law does not split the named sum into a valid "liquidated damages" clause and a void "penalty" clause. Both are treated alike. In exams, section 74, Fateh Chand, the upper limit and proof of loss earn the marks. In real life, it decides how much a seller can keep of an advance, or how much a buyer can deduct for delay.
Exam focus
- Frequency: Rarely asked
- Usually asked as: Long answer (10 to 15 marks)
Legal provision
- Section 74: when a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused by it, to receive from the party who broke the contract reasonable compensation not exceeding the amount so named or the penalty stipulated for.
- Explanation: a stipulation for increased interest from the date of default may be a stipulation by way of penalty.
- Exception: a person who gives a bail-bond, recognizance or similar instrument, or a bond for the performance of a public duty or an act in which the public are interested, is liable to pay the whole sum on breach. A person who contracts with Government does not by that alone undertake a public duty.
- Section 73: compensation for loss that naturally arose from the breach, or that the parties knew to be likely, and not for remote and indirect loss.
Meaning and definition
Liquidated damages are a sum that the contract fixes in advance as payable on breach. Unliquidated damages are not fixed in advance. The court assesses them after the breach, under section 73. A penalty is a stipulation that is meant to frighten a party into performing, and that is out of proportion to the loss likely to follow.
Under English common law, a sum that was a genuine pre-estimate of loss was enforced as liquidated damages, and a sum in the nature of a penalty was not enforced. In Fateh Chand v. Balkishan Dass the Supreme Court said that section 74 is "an attempt to eliminate the somewhat elaborate refinements" of that English distinction. It laid down one rule for both kinds of clause: reasonable compensation not exceeding the sum named.
The flowchart shows how a court applies section 74.
- 1. Was the contract broken, and did the breach cause loss or damage?No: there is nothing to compensate. Damage or loss caused is a necessary condition of section 74.
- 2. Does the contract name a sum payable on breach, or contain any other stipulation by way of penalty, such as forfeiture of money already paid?No: the court assesses unliquidated damages under section 73.
- 3. Can the actual loss be proved?Yes: proof is not dispensed with. The claimant must prove it. If the loss is difficult or impossible to prove, and the sum is a genuine pre-estimate, the sum may be awarded.
- 4. Fix the amount.The court awards reasonable compensation, applying the principles of section 73. The sum named or the penalty stipulated is the upper limit.
Detailed explanation
Step 1: section 74 applies to every named sum
The words "a sum is named" and "any other stipulation by way of penalty" cover two kinds of clause. One names an amount to be paid after breach. The other, such as a forfeiture clause, is a stipulation by way of penalty. In Fateh Chand the Court held that the section applies to "every covenant involving a penalty", including the forfeiture of money already paid.
The section also applies whether the party seeking relief is a plaintiff or a defendant. A buyer who sues for the return of his deposit, and a seller who relies on the forfeiture clause as a defence, both come under it.
Step 2: reasonable compensation up to the sum named
The court does not simply award the sum named. It awards reasonable compensation, and the sum is the ceiling. In Fateh Chand, a buyer who defaulted on a house sale had paid Rs 25,000, made up of Rs 1,000 earnest money and Rs 24,000 towards the price. The contract said the Rs 25,000 would be forfeited. The seller proved no loss. The Court allowed him to keep only the Rs 1,000.
The Court also said that "whether or not actual damage or loss is proved" dispenses only proof of the exact amount. It does not allow compensation when the breach caused no legal injury.
Example. A contractor agrees to pay Rs 1,000 for each week of delay. He is four weeks late, and the employer loses Rs 2,500. The employer may claim up to Rs 4,000, but the court awards reasonable compensation. If the employer proves a Rs 2,500 loss, that is what he gets.
Step 3: when proof of loss is needed
The law on proof is stated in Kailash Nath Associates v. Delhi Development Authority (2015). The phrase "whether or not actual damage or loss is proved" means that where actual loss can be proved, proof is not dispensed with. Only where loss is difficult or impossible to prove can the liquidated sum be awarded, if it is a genuine pre-estimate of the loss. The Court also held that damage or loss caused is a necessary condition for section 74 to apply.
In Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (2003), pipes were supplied late, and ONGC deducted liquidated damages. The Court held that where the sum is a genuine pre-estimate, the party claiming it need not prove actual loss. The burden is on the other party to show that no loss was likely. In Construction and Design Services v. Delhi Development Authority (2015), a sewage pumping station was delayed. The Court said loss could be presume for a public utility project without specific proof, and the burden lay on the contractor to show that the clause was a penalty. Because the clause fixed only a maximum, the Court awarded half of the amount claimed.
Step 4: the stipulated sum is a cap, not a floor
The claimant cannot ask for more than the sum named. In Mahanagar Telephone Nigam Ltd. v. Tata Communications Ltd. (2019), the purchase order capped liquidated damages at 12 per cent. The Court held that a higher figure "cannot be awarded" and that anything claimed above the cap had to be refunded.
Example. A seller promises delivery by 31 January and agrees to pay Rs 500 for each month of delay. He is six months late, and the buyer's actual loss is Rs 6,500. The most the buyer can recover is Rs 3,000, which is six months at Rs 500.
Step 5: forfeiture of earnest money, two lines of authority
The Supreme Court has spoken in two ways on the forfeiture of earnest money. In Maula Bux v. Union of India (1969), the Court said that forfeiture of a reasonable amount paid as earnest money does not impose a penalty, so section 74 does not apply. But if the forfeiture is by way of penalty, section 74 applies. In Kailash Nath (2015), the Court held that section 74 applies to forfeiture of earnest money under a contract, so that the claimant must still show loss. It added that section 74 does not apply where forfeiture takes place under auction terms before any agreement is reached.
In K.R. Suresh v. R. Poornima (2025), the Court noted both lines. It held that a clause forfeiting earnest money is not penal in the ordinary sense, so section 74 did not apply to the Rs 20,00,000 advance in that agreement. It also held that, even if section 74 applied, forfeiture was justified because the vendors had proved losses larger than the amount forfeited.
Step 6: increased interest and the exception
The Explanation says that a stipulation for increased interest from the date of default may be a penalty. The Act's illustration (d) shows a bond for Rs 1,000 at 12 per cent, with 75 per cent interest from default. That is a penalty, and the creditor recovers only reasonable compensation. The exception makes a bail-bond, recognizance, or a bond for a public duty payable in full.
Step 7: the English comparison
Lord Dunedin's tests in Dunlop Pneumatic Tyre Co. v. New Garage and Motor Co. (1915) asked whether the sum was a genuine pre-estimate or extravagant compared with the greatest conceivable loss. In Cavendish Square Holding BV v. Makdessi (2015), the UK Supreme Court replaced the genuine pre-estimate test with a test of whether the clause imposes a detriment out of all proportion to a legitimate interest of the innocent party. Indian law did not need either test, because section 74 itself fixes reasonable compensation up to the sum named.
Illustrations to section 74 at a glance
| Illustration | Facts in short | Result |
|---|---|---|
| (a) | A promises B Rs 1,000 if he fails to pay Rs 500 on a day | B recovers reasonable compensation, not above Rs 1,000 |
| (b) | A promises B Rs 5,000 if he practises as a surgeon in Calcutta, and he does | B recovers reasonable compensation, not above Rs 5,000 |
| (c) | A gives a recognizance of Rs 500 to appear in court and forfeits it | He is liable for the whole penalty (the exception) |
| (d) | A bond for Rs 1,000 at 12 per cent carries 75 per cent interest from default | A penalty, so reasonable compensation only |
| (e) | A debtor promises 10 maunds of grain and 20 maunds on default | A penalty, so reasonable compensation only |
| (f) | A loan of Rs 1,000 is repayable in five instalments, and the whole is due on default | Not a penalty, and the contract is enforced as written |
| (g) | A borrows Rs 100 and gives a bond for Rs 200 payable in instalments, the whole due on default | A penalty |
Don't confuse: liquidated damages, penalty, unliquidated damages and earnest money
All four involve money on breach. They differ in who fixes the sum and what the court does with it.
| Point | Liquidated damages | Penalty | Unliquidated damages | Earnest money |
|---|---|---|---|---|
| Who fixes the sum | The contract | The contract | The court, after breach | The contract, paid at the start |
| Purpose | To estimate the loss | To frighten into performing | To compensate the proved loss | To bind the bargain |
| Indian law | Section 74: reasonable compensation up to the sum | Section 74: the same rule | Section 73 | A reasonable amount may be forfeited (Maula Bux). Kailash Nath applies section 74 |
| Proof of loss | Needed if provable. Not needed if loss is hard to prove and the sum is a genuine pre-estimate | Needed to the extent provable | Always | Depends on the line followed |
Inside the idea. A construction contract says the contractor pays Rs 10,000 for each week of delay, up to 10 per cent of the contract price. The contractor is late, and the employer's loss is hard to prove. The court may award the sum as reasonable compensation, within the cap.
Just outside it. There is no clause about delay, and a supplier is late by a month. The buyer must prove what the delay cost him, and the court assesses it under section 73. This is a claim for unliquidated damages.
Common mistakes
- Applying the English rule that a genuine pre-estimate is enforced in full and a penalty is struck down. Section 74 treats both alike.
- Saying the court awards the named sum automatically. It awards reasonable compensation, up to the sum.
- Saying that no proof of loss is ever needed. Where loss can be proved, proof is not dispensed with.
- Claiming more than the sum named. The named sum is the upper limit.
- Ignoring the two lines on forfeiture of earnest money.
Apply it
Problem
A agrees to erect a plant for B by 31 January 1991 and to pay Rs 500 for each month of delay. A completes the plant six months late. B sues for Rs 6,500, which he says is his actual loss from the delay. What damages is B entitled to?
Issue. Can B recover his actual loss of Rs 6,500, or is he limited by the sum named in the contract?
Rule. Where a sum is named in the contract as payable on breach, the party complaining is entitled to reasonable compensation not exceeding the sum named, whether or not actual loss is proved (section 74). The sum named is the upper limit (Kailash Nath; Mahanagar Telephone Nigam Ltd.).
Application. The contract names Rs 500 for each month of delay. For six months, the sum named is Rs 3,000. B's actual loss of Rs 6,500 is higher than the sum named. B has proved a loss that exceeds the cap, so reasonable compensation is the full Rs 3,000.
Conclusion. B is entitled to Rs 3,000 and no more. He cannot recover the Rs 6,500, because the sum named in the contract limits his claim.
Leading case laws
- Fateh Chand v. Balkishan Dass (1963)
Facts. A buyer agreed on 21 March 1949 to buy a Delhi house for Rs 1,12,500 and paid Rs 1,000 as earnest money and Rs 24,000 on taking possession. He failed to complete the sale, and the contract said the Rs 25,000 would be forfeited. AIR 1963 SC 1405.
Principle. Section 74 applies to a stipulation to forfeit money already paid. The court awards reasonable compensation not exceeding the sum named, and the claimant must show legal injury.
Why it matters. It is the leading case on section 74. The seller kept only the Rs 1,000 earnest money.
- Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (2003)
Facts. Saw Pipes supplied casing pipes to ONGC late, and ONGC deducted US $ 3,04,970.20 and Rs 15,75,559 as liquidated damages. The tribunal ordered a refund. (2003) 5 SCC 705.
Principle. Where the sum is a genuine pre-estimate, the party claiming it need not prove actual loss, and the other party must show that it is unreasonable. The Court set the award aside.
Why it matters. It explains when proof of loss is not required.
- Kailash Nath Associates v. Delhi Development Authority (2015)
Facts. The highest bidder for a DDA plot deposited Rs 78 lakh as earnest money, and DDA cancelled the allotment and forfeited the deposit. The Supreme Court found no breach by the bidder and no loss to DDA, and decided the appeal on 9 January 2015. (2015) 4 SCC 136.
Principle. Section 74 gives reasonable compensation up to the sum named, and loss caused is a necessary condition. It applies to forfeiture of earnest money under a contract, but not to auction terms before any agreement is reached.
Why it matters. It states the law on section 74 in seven points.
- Maula Bux v. Union of India (1969)
Facts. The Union forfeited deposits of Rs 10,000 on a potato contract and Rs 8,500 on a poultry contract after the supplier failed to deliver regularly. (1969) 2 SCC 554.
Principle. Forfeiture of a reasonable amount paid as earnest money is not a penalty. Where loss can be proved, the party must prove it, and the Union had made no attempt to do so.
Why it matters. It is the basis of the line that section 74 does not apply to reasonable earnest money.
- Construction and Design Services v. Delhi Development Authority (2015)
Facts. A contractor was late in building a sewerage pumping station. The contract fixed compensation at 1 per cent of the estimated cost for each day, up to 10 per cent. DDA claimed Rs 20,86,446. The Supreme Court decided on 4 February 2015. (2015) 14 SCC 263.
Principle. Loss may be assumed for a delayed public utility project, and the contractor must show that the clause is a penalty. Where only a maximum is fixed, part of it may be reasonable compensation and part a penalty. The Court awarded half.
Why it matters. It shows how the burden of proof works.
- Mahanagar Telephone Nigam Ltd. v. Tata Communications Ltd. (2019)
Facts. A purchase order capped liquidated damages for delay at 12 per cent. MTNL claimed more by deducting from bills. The Supreme Court decided on 27 February 2019.
Principle. A higher figure cannot be awarded than the contract fixes. Anything claimed above the cap had to be refunded.
Why it matters. It applies the upper limit under section 74.
- K.R. Suresh v. R. Poornima (2025)
Facts. An agreement of 25 July 2007 to sell property for Rs 55,50,000 took an advance of Rs 20,00,000 and gave four months for the balance. The buyer failed to pay, and the vendors forfeited the advance. (2025 INSC 617, decided 2 May 2025.)
Principle. A clause forfeiting earnest money is not penal in the ordinary sense, so section 74 did not apply. Even if it applied, the vendors' proved losses exceeded the amount forfeited.
Why it matters. It is the latest Supreme Court statement on forfeiture of earnest money.
How to write this answer in the exam
5-mark answer
- Define liquidated damages, penalty and unliquidated damages.
- State section 74: reasonable compensation not exceeding the sum named.
- Say that Indian law treats a genuine pre-estimate and a penalty alike.
- Name Fateh Chand.
10-mark answer
- Meaning of the three terms and the text of section 74.
- The English distinction and why Indian law is different (Fateh Chand).
- Reasonable compensation up to the sum named, and the need for proof of loss (Kailash Nath, Saw Pipes).
- Forfeiture of earnest money, with both lines of authority.
- The Explanation on interest, the exception, and the Act's illustrations.
- A short problem applying the cap.
Key points to remember
- Section 74 applies to a named sum and to any other stipulation by way of penalty, including forfeiture.
- The court awards reasonable compensation, and the sum named is the upper limit.
- Indian law does not distinguish liquidated damages from a penalty.
- Where loss can be proved, proof is not dispensed with. It is dispensed with where loss is hard to prove and the sum is a genuine pre-estimate.
- Forfeiture of reasonable earnest money may fall outside section 74 (Maula Bux, K.R. Suresh), though Kailash Nath applies section 74.
- Unliquidated damages are assessed by the court under section 73.
Quick self-test
1. What is the upper limit of compensation under section 74?
The sum named in the contract, or the penalty stipulated.
2. Does Indian law treat liquidated damages and a penalty differently?
No. Section 74 treats both alike and gives reasonable compensation up to the sum named (Fateh Chand).
3. A contract fixes Rs 500 for each month of delay. The seller is six months late and the buyer's loss is Rs 6,500. What can the buyer recover?
At most Rs 3,000, because the sum named is the upper limit.