| Court | Ad hoc Arbitral Tribunal (constituted under the Convention for Settlement of Difficulties Arising from Operation of Smelter at Trail, B.C., 1935) |
|---|---|
| Bench | Jan Frans Hostie (Chairman, Belgium), Charles Warren (United States) and Robert A. E. Greenshields (Canada) |
| Year | 1938 and 1941 (interim decision 16 April 1938; final award 11 March 1941) |
| Cited in | Transboundary Pollution (Notes) |
Smoke from a Canadian smelter drifted across an international border and quietly killed crops and trees in the United States for over a decade. The two governments took their farmers' and industry's dispute to arbitration instead of war or trade retaliation, and the tribunal's answer became the single most-cited sentence in the whole of international environmental law: no country may let its territory be used to seriously harm another's.
United States of America — claimant State, espousing the claims of American landowners and farmers in the state of Washington.
Dominion of Canada — respondent State, answerable for the conduct of the Consolidated Mining and Smelting Company of Canada, operating the smelter at Trail, British Columbia.
The Consolidated Mining and Smelting Company of Canada operated a large lead-zinc smelter at Trail, British Columbia, a few miles north of the Canada–United States border, on the Columbia River. From around 1925, as the smelter's output increased, it emitted large quantities of sulphur dioxide fumes, which drifted south across the international border into the state of Washington, damaging crops, orchards, pasture land and forests over a wide area.
American landowners in Washington sought compensation, and diplomatic protests followed, leading the two governments to agree to submit the dispute to arbitration under the Convention for Settlement of Difficulties Arising from Operation of Smelter at Trail, B.C., signed in 1935. A three-member arbitral tribunal was constituted, chaired by a Belgian jurist with one member nominated by each government, to determine whether the fumes had caused damage in Washington, what compensation was owed, whether the smelter should be required to refrain from causing further damage, and what regime of measures should govern its future operation.
On behalf of the United States: It was argued that the Trail smelter's sulphur dioxide emissions had caused substantial, provable damage to agricultural land, forests and property in the state of Washington over a period of years, that Canada, as the State from whose territory the harm originated, was internationally responsible for ensuring the smelter did not continue to injure United States territory, and that Canada should be required to pay compensation for the damage already caused and to ensure, through an appropriate regime of controls, that further damage was prevented.
On behalf of Canada: While Canada did not dispute that fumes from a privately operated smelter within its territory had drifted across the border, it contested the extent and valuation of the damage claimed, and the scope of any ongoing restrictions that might be imposed on the smelter's future operation, given the smelter's importance to the local economy and the practical difficulty of eliminating fume damage entirely while allowing the plant to continue functioning.
The Tribunal, drawing on general principles of international law including analogous domestic case law on transboundary nuisance between states within federal systems (such as United States Supreme Court decisions on interstate air pollution disputes), held that under the principles of international law, no State has the right to use or permit the use of its territory in such a manner as to cause injury by fumes in or to the territory of another State or the properties or persons therein, when the case is of serious consequence and the injury is established by clear and convincing evidence. This obligation exists independently of any specific treaty provision — it is a general principle of state responsibility applicable whenever one State's territory is used in a way that causes serious, provable transboundary harm to another.
Applying this principle to the facts, the Tribunal found that the fumes from the Trail smelter had indeed caused damage in the state of Washington up to 1 October 1937, and fixed a sum of compensation payable by Canada. Looking forward, rather than ordering the smelter's closure, the Tribunal devised a detailed regulatory regime — a "trail smelter regime" — prescribing maximum permissible emission levels tied to specific meteorological conditions, together with a continuing monitoring and reporting mechanism, under which the smelter could continue to operate while being required to keep future emissions within limits calculated not to cause further serious damage in Washington. The Tribunal thus balanced the recognition of Canada's responsibility to prevent transboundary harm against the practical reality that a complete prohibition of the smelter's operation was not the only means of achieving that end.
The Tribunal awarded the United States compensation for damage caused by the Trail smelter's fumes up to 1 October 1937, held that no State may use or permit the use of its territory in a manner causing serious, provable injury to the territory of another State, and prescribed a detailed regime of emission controls and continuing monitoring under which the smelter was permitted to continue operating while keeping future transboundary damage within tolerable limits.
Under general principles of international law, no State has the right to use, or permit the use of, its territory in a manner that causes serious injury, established by clear and convincing evidence, to the territory of another State or to persons or property therein — this "no-harm" principle applies independent of any specific treaty and is a general incident of state sovereignty and responsibility. Where such transboundary harm is established, a tribunal or state may fashion a remedy going beyond mere compensation, including a forward-looking regulatory regime that permits the harmful activity to continue subject to enforceable limits designed to prevent further serious harm.
The Trail Smelter Arbitration is the single most foundational case in international environmental law, being the source of the "no-harm" principle (sic utere tuo ut alienum non laedas applied to states) that underlies virtually every subsequent development in the field — from the Stockholm Declaration's Principle 21 (which directly echoes the Tribunal's language) through the Rio Declaration, the International Court of Justice's Corfu Channel Case (1949), and the modern law on state responsibility for transboundary environmental harm, including the requirement of prior environmental impact assessment recognised in Pulp Mills on the River Uruguay (Argentina v. Uruguay) (2010). It remains the standard starting point for any discussion of state responsibility for transboundary pollution, and the classic illustration of how a bilateral dispute between two neighbouring states over industrial fumes produced a principle now treated as customary international law.
Facts, tribunal composition and citation verified against the UN Reports of International Arbitral Awards and independent case-law summaries.