Read the full set here, or use the practice card above to test yourself one question at a time.
The Water (Prevention and Control of Pollution) Act, 1974 was enacted under which constitutional mechanism?
Explanation. Since water is a State List subject, Parliament used Article 252 after two or more States passed resolutions requesting central legislation.
Which bodies are established under Sections 3 and 4 of the Water Act, 1974?
Explanation. Sections 3 and 4 establish the CPCB and SPCBs, which also administer the Air Act, 1981.
Before establishing an industry likely to discharge trade effluent into a stream, Sections 25/26 require:
Explanation. Sections 25/26 require prior State Board consent — Consent to Establish before construction, and Consent to Operate before actual operation.
Under Section 33A of the Water Act, the State Pollution Control Board can:
Explanation. Section 33A, inserted in 1988, empowers the Board to issue binding written directions — including closure, prohibition, or regulation — directly, without prior court proceedings.
Under section 1(2) of the Water Act, a State to which the Act did not first apply could bring it into force by:
Explanation. Section 1(2) applied the Act at first to listed States and Union territories. Any other State could adopt it by a resolution under Article 252(1).
The Water (Prevention and Control of Pollution) Amendment Act, 2024 changed the Water Act's enforcement approach by:
Explanation. The Water (Prevention and Control of Pollution) Amendment Act, 2024 came into force on 15 February 2024 and replaced prosecution with a money penalty of Rs 10,000 to Rs 15 lakh for several offences, including section 41.
A factory operates without ever obtaining Consent to Establish or Consent to Operate. Which statement is correct?
Explanation. Operating without the consent mandated by Sections 25/26 is itself a contravention of the Act, regardless of whether actual pollution harm has been separately proved.
Which Section allows the State Board itself to carry out emergency remedial measures against imminent pollution and recover the cost from the polluter?
Explanation. Section 32 empowers the Board to itself take emergency remedial measures where pollution is imminent, and recover the cost from the polluter.